Question: Activity Description Predecessors Duration (mos) A Contract Signing None 1 B Questionnaire Design 2 Target market identification A 2. D Survey Sample B,C 3 E

Activity Description Predecessors Duration (mos)

Activity Description Predecessors Duration (mos) A Contract Signing None 1 B Questionnaire Design 2 Target market identification A 2. D Survey Sample B,C 3 E Develop presentation B 3 F Analyze results D 4 G Demographic analysis C 4 H Presentation to client E, F, G 1 A. THE LATEST TIME TO FINISH THE PROJECT IS B. THE CRITICAL PATH OF THE PROJECT IS