Question: .Activity duration 15 4 weeks, latest start is week 3, earliest finish 15 week 9 and there are 2 weeks of slack Activity duration is

.Activity duration 15 4 weeks, latest start is week 3, earliest finish 15 week 9 and there are 2 weeks of slack Activity duration is 4 weeks, earliest start is week 3, earliest finish is week 7 and there are 2 weeks of slack Activity duration is 4 weeks, earliest start is week 5, earliest finish is week 7 and there are 2 weeks of slack . Activity duration is 4 weeks, latest start is week 5, latest finish is week 7 and there are 2 weeks of slack Activity duration is 4 weeks, earliest start is week 3, earliest finish is week 9 and there are 2 weeks of slack