Question: Activity Duration Dependency Start 0 days A 5 days Start B. 2 days. Start C. 3 days A, B D. 5 days. Start E 6
Activity Duration Dependency Start 0 days A 5 days Start B. 2 days. Start C. 3 days A, B D. 5 days. Start E 6 days Start F 4 days D, E G 2 days C, F H. 5 days G I. 7 days G J. 3 days H Finish 0 days 1,1 Answer this for project scheduling subject. draw forward path , backword path and also activities with same ES AND LF