Question: Find and label each path for the network diagram on the page of the network diagram Find the total float for each path and put
-
Find and label each path for the network diagram on the page of the network
diagram
-
Find the total float for each path and put it beside the path. (IE Path ABCD = TS
4 where TS is the total slack or total float for path ABCD)
-
Find the critical path for the network diagram. Remember: It will have a TS of 0.



Float Float Activity 1 Activity Duration Dependency Start 0 A 2 Start B 5 Start | 6 Start D 1 Start E 6 A F 2 B G 3 C . 7 D 1 E J 9 F K 5 G L 4 H M 3 I, J, K, L End 0 M Critical Path: Activity 2 Activity Duration Dependency Start 0 A 9 Start B 7 Start | 5 Start D 7 A E 5 B F 1 C G 3 D . 4 E . 2 F K 4 G H L 6 | M 2 K, L End 0 . Critical Path: Actirity A > EH- > START 9 J { MACEND AGK D HH Activity k 51827 -- 24-11 -- MHEND I 7 L