Question: Activity Duration Precedent start . 10 w B D E 3 1 start G AE FB D,G Finish 1. Using the above table draw the

Activity Duration Precedent start . 10 w B D E 3

Activity Duration Precedent start . 10 w B D E 3 1 start G AE FB D,G Finish 1. Using the above table draw the network diagram. 2. Using the above table, identify the activities on the critical path in sequence 3. If activity D takes twice as long, describe the effect on the schedule 4. Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. a. day 5 e day 1 b. day 3 d. Cannot be calculated based upon information given