Question: Activity E has an optimistic duration of 1 0 days, most likely duration of 1 5 days, and pessimistic duration of 2 5 days. What

Activity E has an optimistic duration of 10 days, most likely duration of 15 days, and pessimistic duration of 25 days. What is the expected duration of Activity E using the PERT formula?Select one:A.17 daysB.10 daysC.15 daysD.25 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!