Question: Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 18 days. Estimate its

Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 18 days. Estimate its expected time and standard deviation