Question: activity Estimated duration (in months) - optimistic most likely pessimistic 1-2 2 2 14 1-3 2 8 14 1-4 4 4 16 2-5 2 2

activity Estimated duration (in months)
- optimistic most likely pessimistic
1-2 2 2 14
1-3 2 8 14
1-4 4 4 16
2-5 2 2 2
3-5 4 10 28
4-6 4 10 16
5-6 6 12 30

1) find the critical path of the project.

2) find the planned project duration

Show all workings.