Question: activity Estimated duration (in months) - optimistic most likely pessimistic 1-2 2 2 14 1-3 2 8 14 1-4 4 4 16 2-5 2 2
| activity | Estimated duration (in months) | ||
| - | optimistic | most likely | pessimistic |
| 1-2 | 2 | 2 | 14 |
| 1-3 | 2 | 8 | 14 |
| 1-4 | 4 | 4 | 16 |
| 2-5 | 2 | 2 | 2 |
| 3-5 | 4 | 10 | 28 |
| 4-6 | 4 | 10 | 16 |
| 5-6 | 6 | 12 | 30 |
1) find the critical path of the project.
2) find the planned project duration
Show all workings.