Question: A project consists of seven activities whose time estimates are given in the table below: Activity Estimated Duration (in days) - Optimistic Most Likely Pessimistic
A project consists of seven activities whose time estimates are given in the table below:
Activity
Estimated Duration (in days)
-
Optimistic
Most Likely
Pessimistic
1-2
4
10
16
1-3
3
6
9
1-4
4
7
16
2-5
5
5
5
3-5
8
11
32
4-6
4
10
16
5-6
2
5
8
a)Find the critical path of the project.(10 marks)