Question: A project consists of seven activities whose time estimates are given in the table below: Activity Estimated Duration (in days) - Optimistic Most Likely Pessimistic

A project consists of seven activities whose time estimates are given in the table below:

Activity

Estimated Duration (in days)

-

Optimistic

Most Likely

Pessimistic

1-2

4

10

16

1-3

3

6

9

1-4

4

7

16

2-5

5

5

5

3-5

8

11

32

4-6

4

10

16

5-6

2

5

8

a)Find the critical path of the project.(10 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!