Question: An Italian engineering project has the following activities, whose time estimates are listed as follows: Activity Estimated Duration (in months) - Optimistic Most Likely Pessimistic

An Italian engineering project has the following activities, whose time estimates are listed as follows:

Activity

Estimated Duration (in months)

-

Optimistic

Most Likely

Pessimistic

1-2

2

2

14

1-3

2

8

14

1-4

4

4

16

2-5

2

2

2

3-5

4

10

28

4-6

4

10

16

5-6

6

12

30

(a) Find the critical path for the project.

(b) What is the planned project duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!