Question: An Italian engineering project has the following activities, whose time estimates are listed as follows: Activity Estimated Duration (in months) - Optimistic Most Likely Pessimistic
An Italian engineering project has the following activities, whose time estimates are listed as follows:
| Activity | Estimated Duration (in months) | ||
| - | Optimistic | Most Likely | Pessimistic |
| 1-2 | 2 | 2 | 14 |
| 1-3 | 2 | 8 | 14 |
| 1-4 | 4 | 4 | 16 |
| 2-5 | 2 | 2 | 2 |
| 3-5 | 4 | 10 | 28 |
| 4-6 | 4 | 10 | 16 |
| 5-6 | 6 | 12 | 30 |
(a) Find the critical path for the project.
(b) What is the planned project duration?