Question: Activity Expected time (t) in weeks Immediate Predecessors A 5 - B 3 - C 2 A D 5 B E 4 C,D F 7
| Activity | Expected time (t) in weeks | Immediate Predecessors |
| A | 5 | - |
| B | 3 | - |
| C | 2 | A |
| D | 5 | B |
| E | 4 | C,D |
| F | 7 | D |
A. Fill out the network diagram below. Fill in the blanks (ES, EF, LS, LF, t) on the graph. See an example of format to follow on the previous page