Question: Find the project duration & critical path: Activity Duration (Weeks) Immediate Predecessors A 10 - B 4 - C 6 - D 4 B E
Find the project duration & critical path:
Activity Duration (Weeks) Immediate Predecessors
A 10 -
B 4 -
C 6 -
D 4 B
E 1 C, D
F 4 C
G 4 A, D
H 5 E, F
Project Schedule Class Assignment #2 Path Duration A-G 10+4 = 14 weeks B-D-G 4+4+4 = 12 weeks B-D-E-H 4+4+1+5 = 14 weeks C-E-H 6+1+5 = 12 weeks C-F-H 6+4+5 = 15 weeks Your Assignment See blackboard for more information 1. Draw a network diagram depicting the precedence relationships 2. Determine the project schedule (ES/EF, LS/LF)