Question: Activity Expected Time (weeks) Variance Immediate Predecessor Activities A 3 2 None B 5 2 None 3 1 B D 8 3 A, C E

Activity Expected Time (weeks) Variance Immediate

Activity Expected Time (weeks) Variance Immediate Predecessor Activities A 3 2 None B 5 2 None 3 1 B D 8 3 A, C E 5 2 B F 10 2 D, C, E Given the above project, what is the expected project completion time? 20 weeks 26 weeks 15 weeks 25 weeks