Question: QULLUM Compleur Status: Activity Expected Time (weeks) Variance Immediate Predecessor Activities 3 2. None B 5 2 None 3 1 B D 8 3 AC

QULLUM Compleur Status: Activity Expected Time (weeks) Variance Immediate Predecessor Activities 3 2. None B 5 2 None 3 1 B D 8 3 AC E 5 2 B F 10 2 D, C, E Given the above project, what is the expected project completion time? 15 weeks 26 weeks 25 weeks 20 weeks