Question: Activity F has one predecessor activity: activity E. the EF (early finish) of activity E is 18. There fore, the ES(early start) of activity F
Activity F has one predecessor activity: activity E. the EF (early finish) of activity E is 18. There fore, the ES(early start) of activity F is: 24 18 12 6