Question: Activity F has one predecessor activity: Activity E. The EF (earliest finish) of Activity E is 12. Therefore, the ES (earliest start) of Activity F
Activity F has one predecessor activity: Activity E. The EF (earliest finish) of Activity E is 12. Therefore, the ES (earliest start) of Activity F is
A. 12
B. 13
C. 14
D . 15