Question: Activity F has one predecessor activity: Activity E. The EF (earliest finish) of Activity E is 12. Therefore, the ES (earliest start) of Activity F

Activity F has one predecessor activity: Activity E. The EF (earliest finish) of Activity E is 12. Therefore, the ES (earliest start) of Activity F is

A. 12

B. 13

C. 14

D . 15