Question: activity follows optimistic duration most likely direction pessimistic duration A - 4 6 14 B A,C 3 4 5 C - 3 5 13 D

activity follows optimistic duration most likely direction pessimistic duration
A - 4 6 14
B A,C 3 4 5
C - 3 5 13
D A,E 12 18 24
E - 8 10 18
F A,E 4 6 8
G B,F 7 8 9
H G 10 12 14
I G 5 6 7
J D,I 5 7 9

Calculate the probability of completing the project between 35 and 40 weeks? [4 pts] f Answer the project managers question: I want to tell the client that there is a 10.03% chance the project will take longer than X weeks - what figure should I give them (i.e. find X)? [4]