Question: Activity (ID) A B C D E F G H I J Predecessor - - A A A B,C D D,E F G,H Duration (t)

Activity (ID) A B C D E F G H I J
Predecessor - - A A A B,C D D,E F G,H
Duration (t) 5 4 3 4 6 4 5 6 6 4

Problem #1: Given the information for this project.

Part 1 - Develop the network diagram, using the icon provided.

Part 2 - Calculate the total float (TF) and free float (FF) for all activities Part 3 - Identify the critical path(s) by highlighting it in red. You can either use the icon provided and create the diagram, or you can create the diagram using shapes. Either way, you must complete the table on the far right and replace the "?" with the right values. (5 Pts)Part 2 - Calculate the total float (TF) and free float (FF) for all activities

ID ES EF LS LF Total Float Free Float
A ? ? ? ? ? ?
B ? ? ? ? ? ?
C ? ? ? ? ? ?
D ? ? ? ? ? ?
E ? ? ? ? ? ?
F ? ? ? ? ? ?
G ? ? ? ? ? ?
H ? ? ? ? ? ?
I ? ? ? ? ? ?
J ? ? ? ? ? ?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!