Question: Activity ID Slope Max crash time Normal Time Normal Cost Crash Time Crash Cost A 8 $4,000 6 $ 4,500 B 5 $5,500 2 $

Activity ID Slope Max crash time Normal Time Normal Cost Crash Time Crash Cost
A 8 $4,000 6 $ 4,500
B 5 $5,500 2 $ 7,000
C 10 $6,100 7 $ 7,900
D 12 $4,700 9 $ 5,000
E 6 $2,050 4 $ 2,300
F 8 $1,200 6 $ 1,700
G 5 $7,200 4 $ 7,400
H 9 $7,500 7 $ 8,000
I 2 $1,750 2 $ 1,750

Given the above table of Software Developing Project, what is the total normal (direct) cost of the project?

calculate the following:

  • Slope?
  • Maximum crash time?
  • Consider your calculations from the previous question.

    If the critical path is A-B-E-F-I, which activity should be crashed first.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!