Question: Activity Immediate Pred Optimistic Most Likely Pessimistic A None 2 4 6 B None 6 7 11 C A 4 5 12 D A 6
| Activity | Immediate Pred | Optimistic | Most Likely | Pessimistic |
| A | None | 2 | 4 | 6 |
| B | None | 6 | 7 | 11 |
| C | A | 4 | 5 | 12 |
| D | A | 6 | 8 | 10 |
| E | B,D | 6 | 11 | 13 |
| F | B,D | 3 | 4 | 8 |
| G | C,E | 4 | 7 | 10 |
| H | C,E | 3 | 3 | 3 |
| I | F,H | 3 | 4 | 5 |
| J | G | 6 | 8 | 10 |
| K | I,J | 4 | 5 | 6 |
1. Construct the network for this project and,
2. Calculate the ES, LS, EF, LF and Slack for each activity of the project?