Question: Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - - 2 2 . 5 6 B - - 1 0 1 1
Activity Immediate
Predecessor
Optimistic
Time
Most Likely
Time
Pessimistic Time
A
B
C A
D B C
E C
F D E
G E
H F G
a Calculate the expected activity duration te variance for each activity, ES EF LS and LF
times and the slack for each activity. Show the values in a table activity schedule What
is the critical path for the project? Show all work to earn credit.
b Using MS Project or any other software create a Gantt chart for the project based on
ES and EF times.
c What is the probability of completing the project in weeks? Show all work to earn
credit.
d If the activity B can be finished in weeks, D in weeks, and E in weeks, recalculate
the expected project completion time. Show all work.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock