Question: Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - - 2 2 . 5 6 B - - 1 0 1 1

Activity Immediate
Predecessor
Optimistic
Time
Most Likely
Time
Pessimistic Time
A --22.56
B --101112
C A 56.511
D B, C 111315
E C 89.514
F D, E 4.55.59.5
G E 3.556.5
H F, G 6.57.511.5
a. Calculate the expected activity duration (te), variance for each activity, ES, EF, LS, and LF
times and the slack for each activity. Show the values in a table (activity schedule). What
is the critical path for the project? Show all work to earn credit.
b. Using MS Project (or any other software), create a Gantt chart for the project based on
ES and EF times.
c. What is the probability of completing the project in 40 weeks? Show all work to earn
credit.
d. If the activity B can be finished in 10 weeks, D in 11 weeks, and E in 8 weeks, recalculate
the expected project completion time. Show all work.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!