Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
| Activity | Immediate Predecessor (s) | Time (days) |
| A | - | 10 |
| B | - | 6 |
| C | - | 3 |
| D | B | 2 |
| E | A, D | 3 |
| F | C | 6 |
| G | E, F | 12 |
Please give me a detailed explanation of how to calculate slack time for each activity!