Question: Activity Immediate Predecessor Time in Days None 5 B A 2 A 7 D B and C 6 E 15 F B 9 G D,

Activity Immediate Predecessor Time in Days None

Activity Immediate Predecessor Time in Days None 5 B A 2 A 7 D B and C 6 E 15 F B 9 G D, E, F 30 The above table is a simple project listing 7 activities and their respective time estimates: Using CPM, What is the slack for activity D? Select one: a. 6 O b. None of the choices are correct O c. 23 O d. 17 O e. 9