Question: Activity Immediate Predecessor Time in Days None 5 2 B A A 7 D 6 Band C E 15 C F 9 B G 30

Activity Immediate Predecessor Time in Days None
Activity Immediate Predecessor Time in Days None 5 2 B A A 7 D 6 Band C E 15 C F 9 B G 30 A D,E,F,G 10 H The above table is a simple project listing 8 activities and their respective time estimates: Using the Single Time Estimate CPM procedure, what are all of the activities that are not on critical path? Select one: B, C, D, E, F None of the choices are correct C.D.E.G CD B, D, F, G