Question: Activity Immediate Predecessor (Time Weeks) A - 1 B A 4 C A 4 D B 2 E C ,D 5 F D 2 G
Activity Immediate Predecessor (Time Weeks) A - 1 B A 4 C A 4 D B 2 E C ,D 5 F D 2 G F 2 H E, G 3
- Identify critical path
- How many weeks will it take to complete the project?
- Which activities have slack, and how much?