Question: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 14 B A 12 C A 7 D B 4 E B 10 F D 8 G C, E

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 14
B A 12
C A 7
D B 4
E B 10
F D 8
G C, E 5
H F, G 10
I G, H 9

a. What is the early start date for activity H?

b. What is the late finish date for activity B?

c. Determine the minimum number of weeks for completing the project.

d. How many weeks could activity F be delayed without delaying the project?

e. What is the critical path? Enter the activities in capital letters with hyphens (but no spaces) separating the activities. For example, A-C-G.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!