Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 3 C A 5 D B 4 E C D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 2
B A 3
C A 5
D B 4
E C

D
7
F D 2
G F 3
H E

G
7

b. What is the critical path?

multiple choice 1

  • A-B-D-F-G-H

  • A-B-D-E-H

  • A-C-E-H

  • A-C-E-F-G-H

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

multiple choice 2

  • A

    4 weeks

    B

    1 week

    D

    2 weeks.
  • C

    2 weeks

    F

    2 weeks

    G

    2 weeks.
  • B

    2 weeks

    D

    1 week

    E

    4 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!