Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 3 C A 5 D B 4 E C D
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 2 | |
| B | A | 3 |
| C | A | 5 |
| D | B | 4 |
| E | C D | 7 |
| F | D | 2 |
| G | F | 3 |
| H | E G | 7 |
b. What is the critical path?
multiple choice 1
-
A-B-D-F-G-H
-
A-B-D-E-H
-
A-C-E-H
-
A-C-E-F-G-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
- A 4 weeks B 1 week D 2 weeks.
- C 2 weeks F 2 weeks G 2 weeks.
- B 2 weeks D 1 week E 4 weeks.