Question: Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 9 D B 2
Problem 5-8 (Algo)
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 3 | |
| B | A | 4 |
| C | A | 9 |
| D | B | 2 |
| E | C D | 7 |
| F | D | 3 |
| G | F | 4 |
| H | E G | 5 |
b. What is the critical path?
-
A-B-D-E-H
-
A-C-E-F-G-H
-
A-C-E-H
-
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
- B 3 weeks D 3 weeks F 3 weeks G 3 weeks.
- B 2 weeks C 3 weeks E 4 weeks H 1 week.
- B 3 weeks C 2 weeks F 1 week H 2 weeks.