Question: Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 9 D B 2

Problem 5-8 (Algo)

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 9
D B 2
E C

D
7
F D 3
G F 4
H E

G
5

b. What is the critical path?

  • A-B-D-E-H

  • A-C-E-F-G-H

  • A-C-E-H

  • A-B-D-F-G-H

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

  • B

    3 weeks

    D

    3 weeks

    F

    3 weeks

    G

    3 weeks.
  • B

    2 weeks

    C

    3 weeks

    E

    4 weeks

    H

    1 week.
  • B

    3 weeks

    C

    2 weeks

    F

    1 week

    H

    2 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!