Question: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 5 C A 4 D B 3 E C D 4 F D 1 G F

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 2
B A 5
C A 4
D B 3
E C

D
4
F D 1
G F 1
H E

G
2

b. What is the critical path?

  • A-C-E-F-G-H

  • A-C-E-G-H

  • A-B-D-F-G-H

  • A-B-D-E-H

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

  • B

    1 week

    H

    3 weeks

    F

    2 weeks.
  • B

    3 weeks

    C

    1 week

    F

    4 weeks.
  • C

    4 weeks

    F

    2 weeks

    G

    2 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!