Question: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 5 C A 4 D B 3 E C D 4 F D 1 G F
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 2 | |
| B | A | 5 |
| C | A | 4 |
| D | B | 3 |
| E | C D | 4 |
| F | D | 1 |
| G | F | 1 |
| H | E G | 2 |
b. What is the critical path?
-
A-C-E-F-G-H
-
A-C-E-G-H
-
A-B-D-F-G-H
-
A-B-D-E-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
- B 1 week H 3 weeks F 2 weeks.