Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 2 B A 5 C A 4 D B 3 E

Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 2
B A 5
C A 4
D B 3
E C D 4
F D 1
G F 1
H E G 2
b. What is the critical path?
multiple choice 1
A-C-E-F-G-H
A-C-E-G-H
A-B-D-E-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
CPicture 4 weeksPicture FPicture 2 weeksPicture GPicture 2 weeks.
BPicture 1 weekPicture HPicture 3 weeksPicture FPicture 2 weeks.
BPicture 3 weeksPicture CPicture 1 weekPicture FPicture 4 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!