Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 2 B A 5 C A 4 D B 3 E
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E C D
F D
G F
H E G
b What is the critical path?
multiple choice
ACEFGH
ACEGH
ABDEH
ABDFGH
c How many weeks will it take to complete the project?
d Which activities have slack, and how much?
multiple choice
CPicture weeksPicture FPicture weeksPicture GPicture weeks.
BPicture weekPicture HPicture weeksPicture FPicture weeks.
BPicture weeksPicture CPicture weekPicture FPicture weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
