Question: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 5 B A 3 C A 4 D B 6 E C D 8 F D 2 G F
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 5 | |
| B | A | 3 |
| C | A | 4 |
| D | B | 6 |
| E | C D | 8 |
| F | D | 2 |
| G | F | 4 |
| H | E G | 3 |
b. What is the critical path?
A-B-D-F-G-H
A-B-D-E-H
A-C-E-F-G-H
A-C-E-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
A,2 weeks C, 3 weeks; F, 1 week
C, 5 weeks; F, 2weeks; G, 2weeks
B, 1week ; H, 2 weeks ; F, 4 weeks