Question: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 5 B A 3 C A 4 D B 6 E C D 8 F D 2 G F

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 5
B A 3
C A 4
D B 6
E C

D
8
F D 2
G F 4
H E

G
3

b. What is the critical path?

A-B-D-F-G-H

A-B-D-E-H

A-C-E-F-G-H

A-C-E-H

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

A,2 weeks C, 3 weeks; F, 1 week

C, 5 weeks; F, 2weeks; G, 2weeks

B, 1week ; H, 2 weeks ; F, 4 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!