Question: Activity Immediate Predecessors Expected time A - 5 C A 8 D C 2 B A 7 E - 3 F E 6 I B
Activity Immediate Predecessors Expected time
A
C A
D C
B A
E
F E
I BD
M FI
G
H G
K H
end KM
Given the activites above for a business project, the critical path is