Question: Consider a project with the following information. Activity Immediate predecessors Normal time Crash time A 10 8 B 12 11 11 10 D 26 8

Consider a project with the following

Consider a project with the following information. Activity Immediate predecessors Normal time Crash time A 10 8 B 12 11 11 10 D 26 8 E B, C 5 3 What is the total cost of crashing the project by 2 time unit(s)? Crash cost per period $200 $300 $150 $240 $250 Your