Question: 1. (8 points) A project network is given by the following table. Draw the network in your Final Examination Work File and show all path
1. (8 points)
A project network is given by the following table. Draw the network in your Final Examination Work File and show all path lengths. The minimum time required to complete the project is:
| Activity | Immediate Predecessors | Activity Time |
| A | - | 5 days |
| B | A | 10 days |
| C | A | 9 days |
| D | B, C | 7 days |
| E | A | 4 days |
| F | D, E | 3 days |
| G | D, F | 3 days |
A. 15 days
B. 25 days
C. 27 days
D. 28 days
E. 39 days