Question: Activity Immediate Predecessor(s) Time (days) 3 B A 14 A 3 D B S E B 3 F 16 G D 16 H EF G

Activity Immediate Predecessor(s) Time (days) 3 B
Activity Immediate Predecessor(s) Time (days) 3 B A 14 A 3 D B S E B 3 F 16 G D 16 H EF G H a) The earliest finish time of Eis days. b) The latest finish time of Fis days. c) The slack time for Dis days. d) The slack time of C is days