Question: Activity Immediate Predecessors Time in weeks A N/A 3 B A 3 A 6 D B, C 7 E 7 F B 5 G D,

Activity Immediate Predecessors Time in weeks A

Activity Immediate Predecessors Time in weeks A N/A 3 B A 3 A 6 D B, C 7 E 7 F B 5 G D, E 7 H F, G 7 B F D . E What is the earliest start time for activity G