Question: Activity Immediate Predecessor(s) Time (Weeks) A --- 7 B --- 8 C A 12 D B 9 E B 8 F C, D 3 G
| Activity | Immediate Predecessor(s) | Time (Weeks) |
| A | --- | 7 |
| B | --- | 8 |
| C | A | 12 |
| D | B | 9 |
| E | B | 8 |
| F | C, D | 3 |
| G | E, F | 2 |
a) Draw an AON network.
b) What are the critical path and the expected project completion time?
Step by Step Solution
There are 3 Steps involved in it