Question: Activity Immediate Time (weeks) predecessor A - 2 B A 4 C - 3 D C 5 E B, D 2 F E 3 G
Activity Immediate Time (weeks) predecessor A - 2 B A 4 C - 3 D C 5 E B, D 2 F E 3 G B, D 3 H G 6 I H, F 3 Solve the problem and enter your answers to the questions: 1. What are the activities of the critical path? 2. What is the expected completion time for the project (#of weeks)? 3. What is the slack of activity B? 4. What is the latest finish time of activity D? Be sure to enter your answers as follow: For (1) show the activity letters of the critical path. For (2): show the answer is # of weeks.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
