Question: Project Scheduling with Uncertain Time: Activity Immediate Time (weeks) predecessor A 2 B A 6 C 2 D C 4 E B, D 1 F
Project Scheduling with Uncertain Time:
| Activity | Immediate | Time (weeks) | |
| predecessor | |||
| A | 2 | ||
| B | A | 6 | |
| C | 2 | ||
| D | C | 4 | |
| E | B, D | 1 | |
| F | E | 2 | |
| G | B, D | 2 | |
| H | G | 3 | |
| I | H, F | 1 |
Solve the problem and enter your answers to the questions:
1. What are the activities of the critical path?
2. What is the expected completion time for the project (#of weeks)?
3. What is the slack of activity E?
4. What is the latest finish time of activity D?
Be sure to enter your answers as follow:
For (1) show the activity letters of the critical path.
For (2): show the answer is # of weeks.