Question: Activity Immediste Predecessors Optimistic (a) Most likely (m) Pessimistic (b) Expected Time (t) Variance A 3 6 8 5.83 0.69 B A 5 8 10
| Activity | Immediste Predecessors | Optimistic (a) | Most likely (m) | Pessimistic (b) | Expected Time (t) | Variance |
| A | 3 | 6 | 8 | 5.83 | 0.69 | |
| B | A | 5 | 8 | 10 | 7.83 | 0.69 |
| C | A | 5 | 6 | 8 | 6.17 | 0.25 |
| D | B,C | 1 | 2 | 4 | 2.17 | 0.25 |
| E | D | 7 | 11 | 17 | 11.33 | 2.78 |
| F | D | 7 | 9 | 12 | 9.17 | 0.69 |
| G | D | 6 | 8 | 9 | 7.83 | 0.25 |
| H | F,G | 3 | 4 | 7 | 4.33 | 0.44 |
| I | E,F,G | 3 | 5 | 7 | 5.00 | 0.44 |
a) What is the probability the project will be completed in less than 32 weeks?
b) What time should be set such that there is a 95% chance of completion?