Question: Activity No. Activity Time (weeks) Immediate Predecessors 1 Collect requirements 6 2 Analyze processes 2 1 3 Analyze data 4 2 4 Design processes 18
| Activity No. | Activity | Time (weeks) | Immediate Predecessors |
| 1 | Collect requirements | 6 | |
| 2 | Analyze processes | 2 | 1 |
| 3 | Analyze data | 4 | 2 |
| 4 | Design processes | 18 | 2 |
| 5 | Design data | 6 | 3 |
| 6 | Design screens | 6 | 3,4 |
| 7 | Design reports | 12 | 4,5 |
| 8 | Program | 10 | 6,7 |
| 9 | Test and Document | 14 | 7 |
| 10 | Install | 4 | 8,9 |
Construct a network diagram & calculate the earliest expected completion time/s