Question: Activity Normal Time Crash Time Normal Cost Crash Cost Acceleration Cost/Month P 9 8 62.000 72.000 Q 7 5 56.000 86.000 R 8 6 42.000

Activity

Normal Time

Crash Time

Normal Cost

Crash Cost

Acceleration Cost/Month

P

9

8

62.000

72.000

Q

7

5

56.000

86.000

R

8

6

42.000

62.000

S

12

9

66.000

72.000

Total Normal Cost

1. Calculate the acceleration cost/month for each activity.

2. List all paths and their associated total normal time.

Path example: Start -> .... -> .... -> Finish = ... months.

3. Which path is the critical path? Why?

4. How long will it take to finish this project using the normal time?

5. Calculate the total normal cost.

6. If you want to reduce the project duration by 1 month, which activity will you

accelerate? Why? What is the total normal cost + acceleration cost.

7. After reducing the project duration by 1 month, you still want to reduce the project duration by another 1 month for a total of 2 months. Which activity will you accelerate? Why? What is the total normal cost + cumulative acceleration cost.

Activity Normal Time Crash Time Normal Cost Crash

P Q Start Finish R Cost in US$. Time in months

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!