Question: Using the info given before for a project. activity preceded duration (weeks) start a, b, c - a d 5 d f 6 f g
Using the info given before for a project.
| activity | preceded | duration (weeks) |
| start | a, b, c | - |
| a | d | 5 |
| d | f | 6 |
| f | g | 2 |
| b | e | 5 |
| e | f | 9 |
| c | h | 4 |
| h | g, i | 6 |
| g | end | 3 |
| i | end | 1 |
a. please draw the AON (activity to node) graph for this project.
b. please calculate and put your results in table below
| activity | duration | EST | ECT | LST | LCT | Slack time |
| a | 5 | |||||
| b | 5 | |||||
| c | 4 | |||||
| d | 6 | |||||
| e | 9 | |||||
| f | 2 | |||||
| g | 3 | |||||
| h | 6 | |||||
| i | 1 |
c. Given results above, what is the duration of the project
d. Which is the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
