Question: Using the info given before for a project. activity preceded duration (weeks) start a, b, c - a d 5 d f 6 f g

Using the info given before for a project.

activity preceded duration (weeks)
start a, b, c -
a d 5
d f 6
f g 2
b e 5
e f 9
c h 4
h g, i 6
g end 3
i end

1

a. please draw the AON (activity to node) graph for this project.

b. please calculate and put your results in table below

activity duration EST ECT LST LCT Slack time
a 5
b 5
c 4
d 6
e 9
f 2
g 3
h 6
i 1

c. Given results above, what is the duration of the project

d. Which is the critical path