Question: Activity Preceding Activity Normal Completion Time (week) Crashed Completion time (week) Crashed Cost per week A - 6 5 $600 B A 7 5 $700

Activity Preceding Activity Normal Completion Time (week) Crashed Completion time (week) Crashed Cost per week A - 6 5 $600 B A 7 5 $700 C A, B 6 5 $400 D B, C 8 6 $800 E B 5 5 - F D, E 9 8 $500

Highlight the critical and non-critical activities of the finally completed project by taking into account the crashed times of activities