Question: Activity Preceding Optimistic Probable Pessimistic A --- 5 11 14 B --- 3 3 9 C --- 6 10 14 D A,B 3 5 7

Activity

Preceding

Optimistic

Probable

Pessimistic

A

---

5

11

14

B

---

3

3

9

C

---

6

10

14

D

A,B

3

5

7

E

B

4

6

11

F

C

6

8

13

G

D,E

2

4

6

H

F

3

3

9

WITHOUT ROUNDING ANY NUMBER

1. The project duration is: (don't round any number) *

a. 25

b. None

c. 22.5

d. 17

2. The slack time of activity C is: *

a. 8

b. 9

c. None

d. 0

3. The slack time of activity G is: *

a. 8

b. 3

c. None

d. 0

4. The CP contains: *

a. C, F, H

b. A, D, G

c. B, E, G

d. None

5. The duration of activity E is: *

a. 6.5

b. None

c. 5

d. 8

6. The variance of activity H is: *

a. 1

b. 1.7

c. None

d. 2.7

7. The project standard deviation is: (Take one number after the comma) *

a. 2

b. None

c. 2.6

d. 1

8. What is the probability to finish the project before 24 weeks: *

a. None

b. 85.5%

c. 90.9%

d. 77.34%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!