Question: Activity Preceding Optimistic Probable Pessimistic A --- 5 11 14 B --- 3 3 9 C --- 6 10 14 D A,B 3 5 7
| Activity | Preceding | Optimistic | Probable | Pessimistic |
| A | --- | 5 | 11 | 14 |
| B | --- | 3 | 3 | 9 |
| C | --- | 6 | 10 | 14 |
| D | A,B | 3 | 5 | 7 |
| E | B | 4 | 6 | 11 |
| F | C | 6 | 8 | 13 |
| G | D,E | 2 | 4 | 6 |
| H | F | 3 | 3 | 9 |
WITHOUT ROUNDING ANY NUMBER
1. The project duration is: (don't round any number) *
a. 25
b. None
c. 22.5
d. 17
2. The slack time of activity C is: *
a. 8
b. 9
c. None
d. 0
3. The slack time of activity G is: *
a. 8
b. 3
c. None
d. 0
4. The CP contains: *
a. C, F, H
b. A, D, G
c. B, E, G
d. None
5. The duration of activity E is: *
a. 6.5
b. None
c. 5
d. 8
6. The variance of activity H is: *
a. 1
b. 1.7
c. None
d. 2.7
7. The project standard deviation is: (Take one number after the comma) *
a. 2
b. None
c. 2.6
d. 1
8. What is the probability to finish the project before 24 weeks: *
a. None
b. 85.5%
c. 90.9%
d. 77.34%