Consider the network described in the table below. Activity Preceding Optimistic Probable Pessimistic A 5 11 14 B 3 3 9 Ic 6 10 14 D |A, B 3 5 7 E B 4 6 11 F C 6 8 13 G D, E 2. 4 6 H F 3 3 9 Calculate the Variance of the project H F 3 3 9 Calculate the Variance of the project O 1.78 O 1.36 04.14 O 5.82 None of the above