Question: Activity Predecessor Activity Duration Estimate A - 2 B A 2 C A 3 D A 4 E B 2 F C 3 G D
Activity Predecessor Activity Duration Estimate
A
B A
C A
D A
E B
F C
G D
H E F
I E F
J G I
K H J
a Drawn an AON activity on node network diagram representing the project above. Show ES EF LS LF project duration, critical path.
b Identify all the paths of the network diagram and note how long they are.
c What is the shortest possible time it will take to complete this project?