Question: Activity Predecessor Activity Duration Estimate A - 2 B A 2 C A 3 D A 4 E B 2 F C 3 G D

Activity Predecessor Activity Duration Estimate
A -2
B A 2
C A 3
D A 4
E B 2
F C 3
G D 6
H E, F 2
I E, F 5
J G, I 1
K H, J 2
a. Drawn an AON (activity on node) network diagram representing the project above. Show ES, EF, LS, LF, project duration, critical path.
b. Identify all the paths of the network diagram and note how long they are.
c. What is the shortest possible time it will take to complete this project?