Question: Activity Predecessor Duration (weeks) A N/A 2 B N/A 4 C A 2 D N/A 2 E A 3 F C 1 G DE 2
| Activity | Predecessor | Duration (weeks) |
| A | N/A | 2 |
| B | N/A | 4 |
| C | A | 2 |
| D | N/A | 2 |
| E | A | 3 |
| F | C | 1 |
| G | DE | 2 |
| H | EF | 1 |
| I | DH | 1 |
| J | C | 4 |
| K | GHI | 4 |
| L | CEH | 1 |
| M | L | 1 |
| N | KM | 4 |
| O | JK | 4 |
| P | BNO | 1 |
Determine the critical path