Question: Activity Predecessor Activity Duration in Weeks A ---- 3 B A 5 C A 7 D B 10 E C 5 F D, E 4
| Activity | Predecessor Activity | Duration in Weeks |
| A | ---- | 3 |
| B | A | 5 |
| C | A | 7 |
| D | B | 10 |
| E | C | 5 |
| F | D, E | 4 |
Using the Critical Path Method (CPM), find the critical part, activities, and the date to finish the project (Gantt Chart would help).