Question: Activity Predecessor Duration A 2 B 6 C 4 D E C 4 G B, D, E 2 1. Draw a network diagram for the

Activity Predecessor Duration A 2 B 6 C 4 D E C 4

Activity Predecessor Duration A 2 B 6 C 4 D E C 4 G B, D, E 2 1. Draw a network diagram for the activities above with predecessor and duration information. 2. Construct a table with Earliest Start Time, Earliest Completion Time, Latest Start Time, and Latest Completion Time based on the network diagram. 3. Calculate the slack for each activity and based on it, determine the Critical Path. How long can you delay the activities B and E from the Earliest Start Time and yet not delay the overall project completion time